Competency 309.3.2: PERT/CPM Techniques – The graduate correctly applies;PERT/CPM techniques to project management tasks.

Competency 309.3.2: PERT/CPM Techniques – The graduate correctly applies;PERT/CPM techniques to project management tasks.
Objectives:
309.3.2-01: Determine the critical path identified by a given PERT/CPM analysis.
309.3.2-02: Utilize PERT analysis to determine the probability that a given project will meet a specified deadline for completion.
309.3.2-03: Determine slack time for a given project activity.
309.3.2-04: Determine scheduled start time for a given project activity.
309.3.2-05: Determine scheduled completion time for a given project activity.
309.3.2-06: Use time-cost trade-offs to appropriately crash a project network.
________________________________________
Introduction:
This task requires candidates to prepare a program evaluation and review technique (PERT) chart and apply critical path method (CPM) techniques.
Given:
Company A is installing a Web-based customer-feedback system to meet customer needs for quick response when rolling out new products. A new product line is rolling out in 48 weeks and the customer-feedback system must be installed and running in time for the new product launch. Table 1.1 in the attached Excel spreadsheet “PERT/CPM Analysis Table” shows three estimates of the time it will take Company A to complete each of the project activities in the customer feedback system project (optimistic, probable, pessimistic).Company B is installing a similar feedback system to accompany a new product line and originally had the same time line as Company A.
Company B just announced that its new product line is ahead of schedule and will be launched in 44 weeks instead of the initially projected 48 weeks. Because the Web-based customer feedback system must be installed and running in time for the revised date of the product launch, something must be done to shorten implementation time required for the customer-feedback system project. Refer to Table 1.2 in the attached Excel spreadsheet “PERT/CPM Analysis Tables” that lists the expected time it will take to complete the activities if shortened as much as possible (crash time), the cost to complete the activity using normal resources (normal cost), and the cost of completing the activity on an accelerated basis (crash cost).
Task:
A.  Use the estimates for Company A in Table 1.1 to do each of the following:
1.  Determine the expected completion time for each of the nine project activities.
a.  Enter all your answers in Table 1.1, showing all of your work.
2.  Determine the variance for each project activity
a.  Entering all your answers in Table 1.1, showing all of your work.
3.  Prepare a PERT chart showing the network diagram with activity times and their expected durations.
a.  Identify the critical path in the PERT chart.
Note: When the files opens, enter your name and student ID in the respective boxes so the task questions and problems will populate the worksheet. If the attached template does not open or is missing information, please contact Ecare for assistance with opening the file.
Note: Any additional numbers included in the PERT chart will not be evaluated for correctness.
Note: If you don’t have software to build a PERT chart, use text boxes with lines or arrows in a word processing program or a spreadsheet program.
4.  Determine each of the following, showing all of your work or reasoning:
a.  Expected duration of the entire project
b.  Slack for project Activity E
c.  Slack for project Activity C
d.  The earliest week project Activity F is scheduled to start
e.  The latest week project Activity G is scheduled to finish
Note: Referencing a value in the PERT chart is not considered showing work.  Please explain how the value was determined.
5.  Determine the probability of completing this project in time for the product launch in 48 weeks, showing all of your work.
Note: You may want to use the complete cumulative normal table located at;
http://homes.cs.washington.edu/~jrl/normal_cdf.pdf
B.  Use your results from part A1 and the data in Table 1.2 to determine the following:
1.  Maximum reduction in time
a.  Enter your answer for part B1 in Table 1.2, showing all your work.
2.  Crash cost per week
a.  Enter your answer for part B2 in Table 1.2, showing all your work.
Note: For your responses to parts B1 and B2, assume that Company B has the same expected completion times for project activities as Company A.
C.  Identify the following by using your results from part B:
1.  Least costly activities to be crashed in order to complete the project within 44 weeks
2.  Number of weeks each of the activities identified in part C1 should be crashed to meet the deadline with the lowest possible increase in cost
3.  Total additional cost due to crashing of the activities identified in part C1
D.  When you use sources, include all in-text citations and references in APA format.
Note: To reduce unnecessary matches select ignore “small matches <20 words” and “bibliography.” Note: For definitions of terms commonly used in the rubric, see the attached Rubric Terms. Note: When using sources to support ideas and elements in a paper or project, the submission MUST include APA formatted in-text citations with a corresponding reference list for any direct quotes or paraphrasing. It is not necessary to list sources that were consulted if they have not been quoted or paraphrased in the text of the paper or project. Note: No more than a combined total of 30% of a submission can be directly quoted or closely paraphrased from sources, even if cited correctly. For tips on using APA style, please refer to the APA Handout web link included in the General Instructions section. PLACE THIS ORDER OR A SIMILAR ORDER WITH US TODAY AND GET AN AMAZING DISCOUNT ?

Our Service Charter

  1. Excellent Quality / 100% Plagiarism-Free

    We employ a number of measures to ensure top quality essays. The papers go through a system of quality control prior to delivery. We run plagiarism checks on each paper to ensure that they will be 100% plagiarism-free. So, only clean copies hit customers’ emails. We also never resell the papers completed by our writers. So, once it is checked using a plagiarism checker, the paper will be unique. Speaking of the academic writing standards, we will stick to the assignment brief given by the customer and assign the perfect writer. By saying “the perfect writer” we mean the one having an academic degree in the customer’s study field and positive feedback from other customers.
  2. Free Revisions

    We keep the quality bar of all papers high. But in case you need some extra brilliance to the paper, here’s what to do. First of all, you can choose a top writer. It means that we will assign an expert with a degree in your subject. And secondly, you can rely on our editing services. Our editors will revise your papers, checking whether or not they comply with high standards of academic writing. In addition, editing entails adjusting content if it’s off the topic, adding more sources, refining the language style, and making sure the referencing style is followed.
  3. Confidentiality / 100% No Disclosure

    We make sure that clients’ personal data remains confidential and is not exploited for any purposes beyond those related to our services. We only ask you to provide us with the information that is required to produce the paper according to your writing needs. Please note that the payment info is protected as well. Feel free to refer to the support team for more information about our payment methods. The fact that you used our service is kept secret due to the advanced security standards. So, you can be sure that no one will find out that you got a paper from our writing service.
  4. Money Back Guarantee

    If the writer doesn’t address all the questions on your assignment brief or the delivered paper appears to be off the topic, you can ask for a refund. Or, if it is applicable, you can opt in for free revision within 14-30 days, depending on your paper’s length. The revision or refund request should be sent within 14 days after delivery. The customer gets 100% money-back in case they haven't downloaded the paper. All approved refunds will be returned to the customer’s credit card or Bonus Balance in a form of store credit. Take a note that we will send an extra compensation if the customers goes with a store credit.
  5. 24/7 Customer Support

    We have a support team working 24/7 ready to give your issue concerning the order their immediate attention. If you have any questions about the ordering process, communication with the writer, payment options, feel free to join live chat. Be sure to get a fast response. They can also give you the exact price quote, taking into account the timing, desired academic level of the paper, and the number of pages.

Excellent Quality
Zero Plagiarism
Expert Writers

Instant Quote

Subject:
Type:
Pages/Words:
Single spaced
approx 275 words per page
Urgency (Less urgent, less costly):
Level:
Currency:
Total Cost: NaN

Get 10% Off on your 1st order!